Micropower Group AB

Gullhallavägen 20C
352 50 Växjö
Sweden

+46(0) 470 72 74 00
sales@micropower.se
support@micropower-group.com

LinkedIn

Micropower Support Center
Micropower

Micropower's new battery and charger factory reaches a new milestone in 2024

orange line

Micropower's new battery and charger factory is to be completed in 2025. But already during next year, the battery charger production will move to the new facility in Öjaby. The factory will also become the group's new headquarter and Research and development center for battery chargers.

During 2023, the new factory for battery chargers and Lithium-ion batteries have been constructed. Installations in the production area are ongoing, as well as finalizing the construction of the office building. The new factory will have an area of 25’000 m2 with possibility to expand.

Relocation of charger production in 2024

In mid-2024, the project reaches another milestone when the existing battery charger production in Växjö, moves to the new factory in Öjaby. At the same time, the R&D center for battery chargers and the service department, are also moving. Initially, 200 employees will be working in the new factory.

With the new factory, Micropower plans to accelerate its production capacity to meet the increased demand from the market.

"With larger surfaces in combination with increased efficiency, we see the possibility of doubling the number of chargers produced" says Sven Olsson, project manager for the new battery and charger factory.

Local renewable energy and solar cells

In October, Micropower reached an agreement with local energy company, Växjö Energi AB. Micropower will use locally produced renewable energy. The agreement includes district heating, district cooling and ground heating. Another energy source will be solar cells. The battery and charger factory’s solar park will generate approximately 461 MWh.

Unique office building in wooden construction

The office, which will become the group's new headquarter, is shaped like a rotor. It’s not only distinctive in its appearance, but also in its construction. The building's construction is completely made of glulam, and the wooden construction will be visible throughout the office space.
Picture of Rebecca Andersson, Marketing Manager, Micropower Group
Rebecca Andersson

Marketing Manager

rebecca.andersson@micropower.se

Sven Olsson, project manager for Micropower Group's new battery and charger factory
Picture: Sven Olsson, Project Manager for Micropower's new battery and charger factory.
News & Infos

Meet us in 2025

2024/12/24

Micropower

Welcome back to watch the final video this December, where we invite you all to join and explore the world of Micropower.

We Help Customers on Their Electrification Journey

2024/12/17

Micropower

Welcome back to watch the third video this December, where we invite you all to join and explore the world of Micropower in a series of videos that wi...

Meet the People at Micropower - Brilliant People. Seeking Excellence. Every Day.

2024/12/10

Micropower

Welcome back to watch the second video this December, where we invite you all to join and explore the world of Micropower in a series of videos that w...

Welcome to Micropower Group - Your Powerful Solutions Partner

2024/12/03

Micropower

This December, the Micropower Group invites you to explore the world of Micropower through a series of videos that will be published throughout the mo...